The investment cost of the project is 90 million pounds.
The implementation of works at a cost of 30 million pounds has been completed, and the remaining work is estimated at approximately 60 million pounds.
The site was received from the Supreme Council of Antiquities on 10/26/2023.
On 02/08/2024, the Supreme Council of Antiquities’ comments were received regarding the story and scenario of the submitted presentation.
– Nearly 70% of the project has been implemented (control room, drilling works, cable laying, speaker installation, etc.)
It is expected that all work and preparation for the official opening of the display and operation will be completed within two months